Iran-US Claims Tribunal, DIC of Delaware et al. v. Tehran Redevelopment Corp., YCA 1986, at 332 et seq.

Title
Iran-US Claims Tribunal, DIC of Delaware et al. v. Tehran Redevelopment Corp., YCA 1986, at 332 et seq.
Permission Text
Excerpts from this document are included in TransLex by kind permission of the ICCA.
Table of Contents
Content
332

Award in Case No. 255 (176-255-3) of 26 April 1985

Arbitrators: Nils Mangård (chairman), Richard M. Mosk, Parviz Ansari Moin (dissenting)

Parties:

-

Claimants: DIC of Delaware, Inc., Underhill of Delaware, Inc.

-

Respondents: Tehran Redevelpment Corp., The Government of The Islamic Republic of Iran

Subject matters:

-

jurisdiction of the Tribunal; controlled entity (Art. VII(3) of the Claims Settlement Declaration)

-

law governing assignments of contractual rights

-

validity of an assignment of contractual rights (Iranian law; contractual prohibition on assignment)

-

validity and enforceability of oral agreement; definiteness of contratual terms

-

quantum meruit

-

failure to object to invoices for a lengthy period

-

effect of termination on damage remedy

-

proper exchange rate for awarding damages

-

increase in costs for inflation

-

the Government as a respondent

FACTS

On 2 July 1975, DIC and Underhill, both United States corporations, and a Swiss company called Starrett and Eken S.A. ("Starrett") entered into a contract with the Tehran Redevelopment Corp. ("TRC") to provide technical assistance and management in connection with the construction of the concrete superstructures for eight buildings of a housing project in Iran. These eight buildings comprised Phase I of the 33-building project. DIC, Underhill and Starrett were treated separately throughout the contract and were each assigned separate obligations and a specific percentage remuneration.

DIC, Underhill and Starrett were subsequently engaged by TRC to perform similar work on the successive phases of the Ekbatan project. Contracts for Phase II and Phase IA, covering additional buildings were signed on 1 October 1976. Their provisions were substantially the same as the contract for Phase I. Claimants 333 contend that a fourth agreement was orally entered into on or before 9 September 1977 relating to Phase III of the project, while Respondents denied the existence of such an agreement. Asserting that certain payments under these agreements had not been made, Claimants and Starrett sent TRC notices of default on 28 June 1978. These notices provided for termination of the contracts if no payments were made. Claimants brought this Claim for the outstanding payments, which they alleged amounted to US $3,110,626. They also sought US $3,321,53 as the amount they would have earned in the absence of certain alleged breaches by Respondents, and payment for extra work performed, plus interest and costs. TRC asserted counterclaims that sought, inter alia, reimbursement of payments previously made, damages for defective performance and delay, and return of certain documents. All of the counterclaims were dismissed on the merits.

EXTRACT

[...]

337

[...]

The arbitrators then considered the specific claims for payment of the invoices submitted for additional amounts that would have been earned in the absence of certain breaches by Respondents, and for extra work performed. They denied the claim for extra work as unproven, and awarded US$ 2,772,670 as payment of the invoices and US$ 795,000 for amounts that would have been earned. The arbitrators made the following points of general interest:

"It appears from the record before the Tribunal that TRC did not at the time of the submission of the final requisitions object to the specific figures in these requisitions. In addition it does not appear that TRC raised significant objections to the figures in previous requisitions. There is one reference to a disagreement over requisition No. 12 in Phase I, thus showing that if TRC did object, it transmitted those objections. Until October 1977, TRC actually made payments, although none within the specified period for payment. The Respondents submitted to this Tribunal certain requisitions showing handwritten modifications and a direction by someone who appears to work for TRC that payments of modified amounts be made to the Contractors. These modifications were not major. It appears that the modified sums were paid, but it can be inferred that the Contractors did not accept the modifications because such modifications were not incorporated into subsequent requisitions.

(....)

"TRC asserts that it paid more than reflected on the requisitions. Yet, it never objected to the amounts shown as paid upon receiving the requisitions . . . .

(....)

"The failure to dispute an account for a lengthly [sic] period of time at least places a burden on TRC to demonstrate that the account was not accurate. See R. J. Reynolds Tobacco Company and Iran, Award No. 145-35-3 (6 August 1984) [Yearbook Vol. X (1985) p. 258]. As discussed supra, TRC has not 338 provided sufficient evidence justifying its failure to object to the requisitions. In the absence of an audit to be done at the completion of the work and in view of the circumstances set forth above, the amount contained in the requisitions shall be deemed to be an accurate reflection of what is owed to the Claimants for the percentage of work completed. This amount . . . constitute[s] damages for breach of the contracts. It should be noted that although the laws of various countries are not in full accord, the better view and the view adopted by this Chamber is that termination of the contract does not preclude a damage remedy. Morrison-Knudsen Pacific Limited and Ministry of Roads and Transportation, Award No. 143-127-3 (13 July 1984); see The French Civil Code, Art. 1184 para. 2; Treitel, 'Remedies for Breach of Contract' in VII International Encyclopedia of Comparative Law 145-47 (1976).

[...]